| Construction status - Febraury, March 2010 |
|
|
|
|
|
The entire project reached the finishing stage. In buildings 5, 6 and 7, the ceramic tiles are being set up in all the apartments. Central heating systems will be installed this month in each building. The elevators started to function and all the external flooring will start on the second week of April.
|
|
|
|